| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Rights of Way (ROW) Management |
Identifies stakes and easement limits |
Obtains construction easements and work permits |
| Contractor Payments |
Computes quantity measurements |
Develops contractor payment estimates |
Verifies contractor payment estimates |
Recommends contractor payment estimates |
| Documents for application to contractor payments |
Approve contractor payment estimates |
| Supplemental Agreements (change orders) |
Explains general change order procedures |
Provides information to write change orders |
Prepares change orders |
Approves change orders |
| Documents quantities |
Recommends change orders |
| Corrects quantities |
Applies negotiation skills within contract limits. |
| Force accounts |
Explains general force account procedures |
Prepares force accounts |
Directs labor, equipment and materials |
Prepares plan and guide estimates |
| Documents quantities |
| Corrects quantities |
| Cost Estimating |
Computes quantities |
Applies basic principles of cost estimating |
Utilizes historical bid prices to obtain prices for new or negotiated items |
Develops estimate using labor, equipment, materials and historical item prices |
| Claims Management |
Recognizes work falling outside the scope of the contract |
Maintains proper project records |
Implements claims management and contract claims specifications processes and procedures |
Manages project to minimize claims |
| Prepares construction diaries |
Summarizes project records |
Applies claims management process and procedures |
| Negotiates claims |
| Preconstruction (field design/ redesign) |
Identifies basic elements of a construction plan |
Visualizes complete components of the plan |
Modifies basic design (field) using available design tools |
Approves design changes that can be made in the field |
| Locates worksite features included on the construction plan |
Identifies design conflicts or omissions |
Escalates design issues that must be escalated to the designer of record |
| Distinguishes among the plan, profile and cross section |
| Project Closeout |
|
Explains the principles underlying the construction contractor performance evaluation process |
Prepares project closeout documents |
Completes project closeout procedures |
| Prepares objective construction contractor performance evaluation |
Recommends project acceptance |
| Specifications |
Relates specifications to project requirements |
Identifies order of precedence of specifications |
Interprets specifications for change orders |
Writes specifications for change orders |
| Applies specifications in enforcing contract requirements |
| Office Procedures |
Follows office filing procedures for project |
Prepares project-relevant reports and correspondence |
| Scheduling |
Follows project schedule in the execution of assigned work activities |
Interprets project schedule |
Monitors project schedule |
Reviews contractor schedule modifications |
| Uses scheduling tools |
| Partnering |
Applies principles of partnering with contractors and other involved parties |
Participates in partnering with contractors and other involved parties |
Fosters partnering with contractors and other involved parties |
| Value Engineering |
|
|
Recommends VECP actions |
Approves VECP actions |
| Evaluates VECP |
| Consultant Construction Engineering & Inspection (CCEI) |
|
Monitors and documents CCEI services |
Selects and contracts for professional services |
Selects and negotiates CCEI contracts |
| Supervises small project teams |
Establishes project staffing levels and qualifications |
Approves modifications to CCEI contracts |
| Evaluates CCEI Services |
Processes error and omission claims |
| Recommends CCEI contract modifications |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| General |
|
Explains the environmental stipulations regarding erosion and siltation, pollution (water, air, & noise), forests and archeological, paleontological, and rare mineralogical findings |
| Disposal Areas |
|
Explains the procedures that a contractor must follow in securing the approval of a disposal site |
Conducts claims reviews |
| Explains the contents of a contractor's site plan for a disposal area |
Negotiates and resolves issues |
| Explains the responsibilities of both the contractor and the DOT as they pertain to disposal areas |
Approves work orders |
| Environmental Permits, Certificates and Licenses (Streams & Wetlands |
Describes Environmental Permits, Certificates and Licenses |
Verifies that all appropriate permits have been obtained |
Conducts claims reviews |
| Reviews Environmental Permits, Certificates and Licenses for project-applicable commitments |
Verifies that the contractor adheres to the provisions of all environmental permits |
Negotiates and resolves issues |
| Verifies that all permits and special provisions are maintained on-site and the dates are still applicable (expiration dates are current) |
Verifies that the contractor has not caused the rutting, compaction and pollution or other harm to the wetland mitigation planting area |
Approves work orders |
| Verifies that all new pipes and/or culverts for road crossings on perennial streams are being countersunk a minimum of 6 inches for the establishment of natural habitat and that prescribed low-flow provisions are followed |
Verifies that all "no impact" jurisdictional areas are marked off and protected prior to construction |
| Verifies that the contractor is using mats in wetland areas to support construction equipment |
Verifies that all temporary structures in jurisdictional permitted areas are properly maintained |
| Verifies that the contractor has submitted for approval the design and method of temporarily relocating streams to facilitate construction |
Verifies that the contractor has prevented stream constriction which would reduce flows below the prescribed minimum (normally 50%) |
| Verifies that all disturbed jurisdictional stream and wetland areas are returned to natural contours |
| Cultural Resources |
Verifies that all cultural resources (archaeological sites, historic buildings, etc.) that have been delineated on construction plans for avoidance are being protected from impact from construction |
Conducts claims reviews |
| Negotiates and resolves issues |
| Approves work orders |
| Hazardous Materials |
|
Verifies that the site-specific Environmental Plan for the removal and application of protective coatings of metals in structures has been sent to the contractor |
Conducts claims reviews |
| Verifies that during the startup and removal portions of the coating removal process the contractor's certified Industrial Hygienist, Licensed Lead Supervisor or Steel Structure Painting Council Supervisor (as identified in the Environmental Plan) is on site |
Negotiates and resolves issues |
| Verifies that the contractor has collected air samples during the application and removal of protective coatings and has submitted the analysis results as specified |
Approves work orders |
| Verifies that the contractor has a Spill Prevention Control and Countermeasure Plan on-site and adequate secondary containment for petroleum storage if more than a total of 1320 gallons of petroleum product is stored (55-gallon containers and greater) on the project |
| Verifies that fuels and lubricants are stored outside of flood plains and that impoundments are in place to contain accidental spills and prevent such spills from entering waterways |
| Erosion and Sediment Control |
Verifies that the contractor is inspecting and immediately responding to install and correct or maintain erosion and siltation measures so they function properly or when conditions dictate |
Verifies that the contractor has installed temporary and permanent devices to control erosion and minimize siltation of waterways and adjacent properties |
Conducts claims reviews |
| Verifies that the contractor has a fully certified erosion and sediment control employee on the project during any land disturbing operations |
Negotiates and resolves issues |
| Verifies that the contractor has uniformly graded disturbed areas to natural contours to facilitate drainage and prevent impoundment of water |
Approves work orders |
| Verifies that all discharge water is being filtered to remove deleterious materials prior to discharge into state waters |
| Verifies that all excavated materials are being disposed of in an approved area above the mean high water elevation in a manner that will prevent their return into state waters |
| Verifies that the contractor is preventing erosion of soil and the pollution and siltation of rivers, streams, and impoundments during the construction of new bridges and culverts and removal of existing bridges and culverts |
| Debris Burning |
Explains the Specification pertaining to burning debris from construction operations |
Verifies that the contractor's burning has been approved and is in compliance with all applicable laws, rules, and ordinances |
Conducts claims reviews |
| Negotiates and resolves issues |
| Approves work orders |
| Water & Sanitary Sewer Facilities |
|
Verifies that cisterns, septic tanks, and other structures have been demolished and backfilled properly |
Conducts claims reviews |
| Verifies that all wells have been properly closed |
Negotiates and resolves issues |
| Verifies that water supplies are protected from contamination by sewage |
Approves work orders |
| Verifies that water mains and accessories have been disinfected prior to tie-ins in accordance with prescribed procedures |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Permits/Agreements |
Identifies basic elements of permits and agreement forms |
Ensures documentation (permits/agreements) compliance |
Adjusts schedule to accommodate dates of utility relocation work to avoid delay highway contractor |
Coordinates with organizations to arrange for appropriate permits/agreements |
| Follows basic permit and agreement form procedures |
Communicates and works toward resolution of discrepancies or issues |
| Location/Mapping/ Surveying |
Identifies utility locations/mapping |
Relates utility locations/mapping to construction activities (e.g., depths) |
Identifies need for additional mapping/location and relationship with project schedules and delays |
Ensures appropriate action for additional mapping/location and relationship with project schedules and delays |
| Utility Construction |
Recognizes plans, specifications and safety issues related to utility construction |
Identifies construction techniques, specifications and safety issues related to utility construction |
Adjusts schedule to accommodate dates of utility relocation work to avoid delay highway contractor |
Makes appropriate changes and adjustments based on applicable code and pipeline regulations |
| Railroads |
Recognizes need for appropriate permits and staff |
Complies with applicable permits and railroad requirements |
Coordinates with railroad organizations for permits/changes |
| Subsurface Utility Engineering (SUE) |
Locates (plan view) and designates (plan and profile views) utilities on the project |
Assesses utility condition |
Ensures utility operations |
Mitigates conflicts and minimizes utility relocation |
| Verifies survey and utility mapping outputs |
Identifies utility conflicts |
Develops relocation cost estimates |
| Recognizes SUE quality levels |
Resolves accommodation conflicts |
| Implements accommodation policies |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Excavation |
Explains the basic principles of excavation |
Interprets grading stakes |
Recognizes implication of improper application (including effects on and of other structures) |
Determines contract decisions related to excavation, clearing and grubbing, unsuitable material and acceptance of shoring plans |
| Assists in measuring areas for payment |
Explains the basics of haul diagrams in the Contract Plans |
Interprets haul diagram and identifies changes in the field |
Recommends changes in balance points to equalize distribution of excavated material on the jobsite |
| Describes safety issues related to shoring in areas of excavation (OSHA Trenching Safety Requirements) |
Identifies areas requiring shoring and reviews plans |
Recommends acceptance or rejection of shoring plans |
| Distinguishes between materials that can be excavated by conventional equipment (blades, loaders, hoes, rippers, etc.) or by rock excavation techniques (hydraulic & pneumatic equipment, blasting, swelling agents, etc.) |
| Evaluates subgrades (proofrolling, soundings, testpits, etc.) to identify wet or unsuitable subgrade materials and recognizes solution alternatives |
| Controlled Blasting |
|
Explains the basic principles of Controlled Blasting |
Recognizes implication of improper application |
Determines contract decisions related to controlled blasting |
| Identifies safety concerns related to traveling public |
Reviews Contractor's controlled blasting plan |
| Verifies vibration monitoring requirements and results |
| Recommends contract decisions related to controlled blasting |
| Contour Grading |
|
Explains the basic principles of contour grading |
Recognizes implication of improper application |
Determines contract decisions related to contour grading |
| Enforces specifications |
Recommends contract decisions related to contour grading |
| Interprets staking |
| Identifies improper information |
| Site Preparation |
Explains the difference between clearing and grubbing |
Identifies limits of clearing and grubbing for payment |
Recommends acceptance or rejection of limits of clearing and grubbing for payment |
| Recognizes proper soil surface preparations (I.e. benching, surface drainage, scarifying, sealing, etc.) |
Evaluates foundation soils (proofrolling, soundings, testpits, etc.) to identify wet or unsuitable foundation materials and recognizes solution alternatives |
| Identifies limits of wet or unsuitable material and makes recommendations for shallow repair/improvement of area, or notifies geotechnical engineer if other ground improvement methods are warranted |
| Embankment |
Explains the basic principles of embankment construction |
Interprets grading stakes |
Recognizes implication of improper construction of embankment |
Determines contract decisions related to embankment |
| Recognizes unsuitable embankment material |
Recommends acceptance or rejection of embankment material |
Recommends corrective actions to be taken in relationship to improperly constructed embankments |
| Recognizes problems associated with density tests and notifies supervisor |
Interprets results of density tests for acceptance or rejection of compacted materials |
| Recognizes improper slope and embankment construction |
Verifies requirements and results for ground improvement methods used for embankment construction (I.e. vertical drains, reinforced slopes, light weight fill, column supported embankments, etc.) |
| Borrow |
Describes the basic requirements of borrow material |
Identifies limits of borrow site |
Recognizes implication of improper application |
Determines contract decisions related to borrow |
| Collects weigh tickets and identifies area of placement of material |
Observes and documents the reclamation of the borrow site |
Recommends acceptance of rejection of borrow site reclamation plan |
| Identifies representative samples for laboratory testing |
Recommends acceptance or rejection of borrow source |
| Interprets material test result for suitability of material |
| Compaction |
Describes principles of compaction |
Interprets material test result for acceptance or rejection of compactive effort and/or soil moisture |
Recognizes implication of improper application |
Determines contract decisions related to compaction |
| Distinguishes soil types and recognizes moisture-density relationships for all approved soil types and compactive efforts |
Recommends contract decisions related to compaction |
| Reviews results of compaction tests, moisture contents, and field proctor tests as required |
| Recognizes problems associated with density tests and notifies supervisor |
| Documentation |
Measures quantities of material hauled |
Calculates quantities for payment |
Checks calculations and approves payment |
Authorizes payment for all items related to a contract |
| Calculates densities and moisture contents |
Compiles documentation to support contract changes |
Prepares changes to the contract documents |
| Recognizes proper material documentation |
| Writes project diaries |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| General Surface and Subsurface Drainage Systems |
Describes the basic purposes of surface and subsurface drainage systems |
Recognizes proper surface and subsurface drainage system installation procedures |
Recognizes improper surface and subsurface drainage system location staking and recommends corrective actions |
Determines contract decisions related to changed conditions or corrective actions pertaining to surface and subsurface drainage systems |
| Identifies surface and subsurface drainage items on contract plans |
Interprets surface and subsurface drainage system stakes and identifies location problems in the field |
Recommends changes to the location of drainage items to accommodate conflicts in the field (after communicating with engineer) |
| Recognizes special identification, test compliance stamps and certificates on drainage system materials |
Documents acceptance of drainage items and records measurement for payment |
Documents rejection of drainage system work and corrective action taken |
| Conventional Drainage Systems Construction Inspection |
Describes the elements and engineering properties of conventional drainage systems |
Inspects drainage pipe unloading, storage and installation procedures |
Conducts conventional drainage system performance tests |
Determines contract decisions related to changed conditions or corrective actions pertaining to conventional drainage system installations |
| Performs basic inspection of standard manufactured pipe, conduit, fittings and precast elements |
Inspects drainage pipe bedding and backfilling materials and procedures |
Recognizes improper conventional drainage system installation and recommends corrective actions |
| Large and Special Drainage Systems Construction Inspection |
Describes the basic elements of large and special drainage systems such as multi-plate culverts |
Inspects large and special drainage pipe unloading, storage and installation procedures |
Conducts large and special drainage system performance tests |
Determines contract decisions related to changed conditions or corrective actions pertaining to large and special system installations |
| Performs basic inspection of manufactured elements of large and special drainage systems |
Inspects large and special drainage pipe bedding and backfilling materials and procedures |
Recognizes improper large and special drainage system installation and recommends corrective actions |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Surface Preparation |
Assists in performing inspections of the surface upon which the aggregate materials are to be placed |
Inspects subgrade or previously placed aggregate layers surface for required density and cross section in accordance with contract documents |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to surface preparation acceptance and payment |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Stockpiling and Hauling |
Assists in inspecting contractor's aggregate stockpiling methods |
Inspects contractors stockpiling methods |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to stockpiling and hauling vehicle acceptance and payment |
| Assists in performing inspections of hauling vehicles |
Inspects trucks for proper loading and protection of aggregate materials |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Checks weigh tickets for compliance with load restrictions |
| Laydown |
Assists in performing inspections related to laydown of aggregate materials |
Inspects laydown and processing of aggregate materials for compliance with uniformity cross section requirements |
Recommends acceptance or corrective action based on visual inspection and results of jobsite test |
Determines contract decisions related to HMA laydown acceptance and payment |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Compaction |
Describes basic compaction principles and roller patterns |
Identifies types of compaction equipment |
Recommends acceptance or corrective action based on visual inspection and results of jobsite compaction tests |
Determines contract decisions related to laydown and compaction acceptance and payment |
| Explains how the types of compaction equipment are used |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Surface Tolerances/ Smoothness |
Recognizes the factors that control surface smoothness and how equipment is used to measure smoothness |
Interprets results of job surface tolerance and smoothness checks |
Recommends acceptance or corrective action based on visual inspection and results of surface tolerance and smoothness checks |
Determines contract decisions related to surface tolerance and smoothness acceptance and payment |
| Assists in laying out roadway sections for surface tolerance checks |
Calculates pay factors for incentive/disincentive where appropriate |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Documentation |
Selects correct inspection forms to be used for different aggregate layers |
Completes inspection forms |
Documents acceptance or corrective action based on a review of inspection reports, measurements and test results |
Enters data into summary reports or statistical programs |
| Performs basic mathematical calculations |
Interprets data |
| Reports out inspection results |
Recommends corrective action on a program basis to managers |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| General Geotechnical Construction Inspection |
Performs basic geotechnical construction inspection observations, measurements and computations |
Conducts common geotechnical installation acceptance tests and inspects standard installations |
Administers specialized geotechnical installation acceptance tests and unique installation inspections |
Oversees common and specialized geotechnical installation acceptance tests and installation procedures |
| Verifies locations and quantities |
Decides on geotechnical installation acceptance and payment |
| Subsurface Exploration |
|
Assists in performing basic subsurface exploration crew soil boring, coring, sampling tasks |
Reads plans and locates borings |
Supervises standard subsurface exploration boring, coring, sampling, visual description and logging crew operations |
| Determines water levels in borings |
Operates drilling equipment without supervision |
Performs specialized geotechnical field and insitu testing |
| Operates drilling equipment under direct supervision |
Performs standard subsurface exploration boring, coring, disturbed and undisturbed sampling, SPT, visual description and logging tasks, and proper sample storage/transport |
Installs specialized instrumentation |
| Installs common instrumentation |
| Geosynthetic Materials Installation Inspection |
Performs simple geosynthetic materials installation observations, measurements and computations |
Conducts standard geosynthetic materials acceptance and inspects standard installations |
Administers geosynthetic materials specialized acceptance tests and unique installation inspections |
Oversees common and specialized acceptance and installation procedures |
| Verifies locations and quantities |
Decides on geosynthetic materials installation acceptance and payment |
| Shallow Foundation Inspection |
|
Recognizes foundation excavation requirements |
Verifies bearing material |
Recommends corrective actions on foundation bearing after communicating with engineer |
| Recognizes effects of open excavation with respect to time on bearing capacity and performance (I.e. rainwater infiltration, groundwater, soil relaxation, etc.) |
| Driven Foundation Inspection |
Identifies pile foundation types |
Performs standard driven pile foundation inspections |
Correlates estimated and actual driven pile tip elevations to boring logs |
Authorizes payment for all driven foundation items within contract |
| Recognizes elements of an approved driven pile installation plan |
Verifies compliance with the approved installation plan |
Supervises standard driven pile inspection operations |
Assures compliance with contract specifications and approved installation plans |
| Recognizes basic driving control methods |
| Performs basic load testing |
| Drilled Shaft Inspection |
Describes the basics of drilled shaft dry, casing and wet construction methods |
Performs standard drilled shaft installation inspections and |
Supervises standard drilled shaft inspection crew operations |
Authorizes payment for all drilled shaft items within contract |
| Recognizes elements of an approved drilled shaft installation plan |
Verifies compliance with the approved installation plan |
Verifies and documents subsurface soil/rock and groundwater conditions |
Assure compliance with the contract specifications and approved installation plans |
| Recognizes construction and installation equipment components |
| Ground Anchor Inspection |
|
|
Recognizes proper and improper installation |
Communicates with engineer on documented results, and trouble-shooting as required |
| Verifies and documents installation requirements and results (drilling, encountered soil/rock, hole depth, drill-hole integrity, anchors, corrosion protection, proper torque (if applicable), grouting (bonded and unbonded), seating platform and plate/nut assembly, pretensioning, lock-off, and project details) |
| Verifies and documents load test requirements and results |
| Soil Nail Wall Inspection |
|
|
Recognizes proper and improper installation |
Communicates with engineer on documented results, and trouble-shooting as required |
| Verifies and documents installation requirements and results (excavation, benching, nail spacing, drilling, encountered soil/rock, hole depth, drill-hole integrity, nails, corrosion protection, grouting, seating platform and plate/nut assembly, drain installation, mesh/reinforcement placement, shotcreting, and project details) |
| Verifies and documents load test requirements and results |
| Mechanically Stabilized Earth Wall Inspection |
|
Recognizes proper MSE wall construction |
Recognizes improper MSE wall construction and conditions effecting wall performance and stability |
Recommends corrective actions to MSE wall construction after communicating with engineer |
| Verifies compaction and reinforcement placement requirements and documents results |
Oversees wall construction |
| Verifies structural and drainage detail requirements, structural connection requirements, and delivered materials, material requirements, corrosion testing results |
| Reinforced Soil Slopes (RSS) Inspection |
|
Recognizes proper reinforced soil slope construction |
Recognizes improper reinforced soil slope construction and conditions effecting slope performance and stability |
Recommends corrective actions to RSS construction after communicating with engineer |
| Verifies compaction and reinforcement placement requirements and documents results |
Oversees RSS construction |
| Verifies structural and drainage detail requirements, reinforcement splices, delivered materials, material requirements |
| Ground Improvement Inspection |
|
|
Recognizes proper and improper installation of various ground improvement methods |
Communicates with engineer on documented results, and trouble-shooting as required |
| Verifies and documents requirements and results for ground improvement methods, including vertical drains, lightweight fill, vibrocompaction, dynamic compaction, stone columns, vibroconcrete columns, grouting (permeation, compaction, jet, soil fracture, rock fissure, and general pressure grouting), reinforced earth, deep soil mixing, and column supported embankments |
| Verifies and documents results of performance testing, as required |
| Documentation |
Describes the basics of project documentation |
Calculates quantities for geotechnical installations and geosynthetic materials |
Checks calculations |
Authorizes payment for all geotechnical and geosynthetic items related to a contract |
| Writes project diaries |
Approves payment for geotechnical installations and geosynthetic material |
Prepares changes to the contract documents |
| Compiles documentation to support contract changes |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Footings |
Describes types of footings |
Determines specification and geotechnical requirements compliance or corrective action required |
Recommends contract decisions related to foundations acceptance and payment |
Determines contract decisions related to foundations |
| Assists in checking staking for location |
Checks staking for location in relation to plans |
Verifies footing bearing elevation and location |
| Verifies concrete requirements and placement |
Verifies steel reinforcement requirements & placement |
| Retaining Walls (General) |
Describes types of retaining wall systems |
Recognizes wall construction requirements (including concrete, concrete steel reinforcement, backfill, backfill reinforcement, drainage, and plan detail requirements) |
Recognizes improper wall construction and conditions effecting wall performance and stability |
Determines contract decisions related to walls |
| Assists in checking line and grade |
Checks staking for location in relation to plans |
Oversees wall construction |
Recommends corrective actions on foundation and wall bearing after communicating with engineer |
| Verifies concrete requirements & placement |
Verifies foundation and wall bearing subgrade conditions |
| Verifies backfill requirements & placement (See Grading: Compaction) |
Verifies structural and drainage detail requirements, structural connection requirements, and delivered materials, material requirements, material testing results |
| Forming & Falsework |
Explains basic formwork and falsework specifications |
Compares field layout to forming and falsework drawings |
Reviews Contractor's submittals |
Approves formwork and falsework submittals |
| Determines specification compliance or corrective action required |
Recommends contract decisions relating to forming and falsework |
Determines contract decisions related to forming and falsework acceptance and payment |
| Concrete Girders |
Explains the basic types of a concrete girder |
Determines specification compliance or corrective action required |
Recommends contract decisions related to concrete girders acceptance and payment |
Determines contract decisions related to concrete girders acceptance and payment |
| Assists in checking girder deflection |
Checks for proper deflection of girders |
| Observes placement of girder |
| Observes handling and storage of concrete girders |
| Steel girders & connectors |
Explains the basic properties of a steel girder |
Determines specification compliance or corrective action required |
Recommends contract decisions related to steel girders acceptance and payment |
Determines contract decisions related to steel girders acceptance and payment |
| Describes procedure for checking bolts |
Verifies proper bolted connections |
| Verifies for proper sandblasting of steel |
| Inspects painting of girder in field |
| Inspects handling and storage of girder |
| Reinforcing Steel - Layout |
Explains basic reinforcing steel layout specifications |
Identifies proper spacing, tieing and support of reinforcing steel |
Recommends contract decisions related to reinforcing steel layout acceptance and payment |
Determines contract decisions related to reinforcing steel layout acceptance and payment |
| Describes the various types of reinforcing steel |
Observes handling and storage of reinforcing steel |
| Describes handling and storage of different types of reinforcing steel |
Inspects reinforcing steel for damage (rust, damaged epoxy coating) and enforces corrective action |
| Assists in checking reinforcing bar spacing and support |
Compares field layout to contract plans |
| Concrete Placement & Consolidation |
Describes the principles of concrete placement |
Determines specification compliance or corrective action required |
Recommends contract decisions related to concrete placement acceptance and payment |
Determines contract decisions related to placement acceptance and payment |
| Describes proper vibration techniques |
Determines if the concrete is being properly vibrated |
| Determines if the proper pour rate is being maintained |
| Joints |
Describes types of Joints |
Determines specification compliance or corrective action required |
Recommends contract decisions related to steel girders acceptance and payment |
Determines contract decisions related to then acceptance of joints and payment |
| Compares layout of joints to plans and determines if proper material is used to construct joint |
| Finishing & Curing Concrete |
Describes methods of finishing and curing concrete |
Determines specification compliance or corrective action required |
Recommends contract decisions related to finishing and curing concrete and payment |
Determines contract decisions related to finishing concrete |
| Assists in checking rails for deck finishing machine |
Observes setup of deck finishing machine and checks for proper deck thickness |
Documents and follows up on corrective actions |
Approves removal of curing system |
| Assists in checking the application of curing compound |
Inspects the application of curing compound and checks to make sure the curing system is maintained |
Recommends approval of removal of curing system |
| Deck Smoothness |
Describes the requirements for smoothness |
Determines specification compliance or corrective action required |
Recommends contract decisions related to smoothness acceptance and payment |
Determines contract decisions related to smoothness |
| Demonstrates the proper technique for using a straightedge |
Checks smoothness |
| Precast Structures |
Identifies precast items on construction plan |
Recognizes proper precast structure installation procedures |
Recognizes implications of improper installation |
Determines contract decisions related to changes or corrective actions regarding precast units |
| Recognizes precast products and materials acceptance stamps/certifications |
Identifies location problems in the field |
Recommends corrective actions |
| Identifies product defects prior to installation |
Recommends changes to the location of precast units to accommodate conflicts in the field |
| Recommends acceptance or rejection of precast units |
| Post Tensioning |
|
Checks strand condition, certification of post-tensioning equipment (jack) |
Monitors load and measures elongation |
Recommends corrective action or rejection of product |
| Inspects pre-tensioning preparations |
Documents and calculates elongation for acceptance |
| Verifies post tensioning layout |
Recognizes implications of improper installation of grout |
| Assists in monitoring tensioning sequence |
| Inspects grouting operations |
| Documentation |
Describes the basics of project documentation |
Calculates quantities for payment |
Checks calculations and approves payment |
Authorizes payment for all items related to a contract |
| Writes project diaries |
Compiles documentation to support contract changes |
Prepares changes to the contract documents and recommend approval |
| Documents acceptance of precast units |
| Records measurements for payments |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Surface Preparation |
Assists in performing surface inspections |
Inspects surface for proper preparation in accordance with contract documents |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to surface preparation acceptance and payment |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Concrete Delivery |
Assists in inspections of delivery vehicles to make sure they are in good working condition |
Inspects trucks to assure that all gauges, meters, etc. are in working order |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to concrete delivery acceptance and payment |
| Checks for worn parts that could affect mix quality |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Collects load tickets |
| Verifies correct mix was shipped |
| Paving Machine |
Assists in inspecting paving machine to determine that it is in good working condition |
Inspects paving machine to make sure it is in good working condition |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to paving machine acceptance and payment. |
| Checks to ensure that the machine is set up correctly to place concrete at the specified thickness, profile and finish. |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Laydown (placement)/ Consolidation |
Assists in performing inspections of laydown/consolidation of materials in accordance with job specific requirements |
Inspects laydown/consolidation of materials to meet job specific requirements |
Recommends acceptance or corrective action based on visual inspection and results of jobsite measurements |
Determines contract decisions related to placement and consolidation acceptance and payment |
| Documents and follows up on corrective actions |
| Steel Placement |
Assists in performing inspections of steel and placement |
Inspects placement of steel to meet job specific requirements |
Recommends acceptance or corrective action based on visual and jobsite inspection of steel placement |
Determines contract decisions related to steel placement acceptance and payment |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Smoothness |
Recognizes the factors that control smoothness and how equipment is used to measure smoothness |
Interprets printouts of smoothness readings |
Recommends corrective action based on visual inspection and results of smoothness tests actions |
Determines contract decisions relating to smoothness acceptance and payment. |
| Assists in laying out roadway sections to be measured for smoothness |
Calculates pay factors for incentive/disincentive where appropriate |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Dowels/Joints |
Assists in performing inspections of dowel placement and joints to meet job specific requirements |
Performs inspection of dowel placement and joints to meet job specific requirements |
Recommends acceptance or corrective action based on visual inspection |
Determines contract decisions related to dowel placement and joints acceptance and payment. |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Documentation |
Selects correct forms to be used in documenting inspections |
Completes inspection reports |
Documents acceptance or corrective action based on a review of test results, inspection reports and visual observations |
Interprets data |
| Conducts field tests |
Recommends corrective action on a program basis to managers |
| Documents equipment inspection |
Enters data into summary or statistical program |
| Performs basic mathematical calculations and report out results |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Surface Preparation |
Assists in performing inspections of surface preparation |
Inspects surface for proper preparation in accordance with contract documents |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to surface preparation acceptance and payment. |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Hauling |
Assists in performing inspections of hauling vehicles |
Inspects trucks for proper loading and protection of Hot Mix Asphalt material |
Recommends acceptance or corrective action based on inspection results |
Determines contract decisions related to hauling vehicle acceptance and payment |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Laydown |
Assists in performing inspections related to laydown of HMA |
Inspects laydown of material to meet job specific requirements |
Recommends acceptance or corrective action based on visual inspection and results of jobsite tests |
Determines contract decisions related to HMA laydown acceptance and payment. |
| Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Compaction |
Describes basic compaction principles and roller patterns |
Determines adherence to roller operation and roller plan |
Recommends acceptance or corrective action based on visual inspection and results of jobsite tests |
Determines contract decisions related to laydown and compaction acceptance and payment. |
| Identifies types of compaction equipment |
Documents and follows up on corrective actions |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Explains how the types of compaction equipment are used |
| Smoothness |
Recognizes the factors that control smoothness and how equipment is used to measure smoothness |
Interprets printouts of smoothness readings |
Recommends acceptance or corrective action based on visual inspection and results of smoothness tests |
Determines contract decisions related to smoothness acceptance and payment |
| Assists in laying out roadway sections to be measured for smoothness |
Calculates pay factors for incentive/disincentive where appropriate |
Recommends disciplinary action when corrective measures are not taken in a reasonable time frame |
| Documentation |
Selects correct inspection forms to be used for different layers and types of HMA |
Performs basic mathematical calculations |
Documents acceptance or corrective action based on a review of inspection reports, measurements and test results |
Enters data into summary reports or statistical programs. |
| Reports out inspection results |
Interprets data |
| Recommends corrective action on a program basis to managers |
| Disciplines |
Competencies by Skill Levels |
| Level I |
Level II |
Level III |
Level IV |
| Horticultural Practices |
Explains plant growth and planting methods |
Inspects, and records plant types, topsoil characteristics, soil amendments, pruning, staking and guying procedures |
Reviews inspection records and results |
Approves or rejects results of the inspection and review of plant types, topsoil, amendments, pruning, staking and guying procedures, nursery landscaping inspection, plant diseases and pests and landscaping establishment |
| Reads planting plans |
Inspects and determines plant diseases and pests |
Recommends acceptance or rejection of plant types, topsoil, amendments, pruning, staking and guying procedures, nursery plant inspections, landscaping diseases and pests, and landscaping establishment |
Distinguishes plant diseases and pests |
| Describes pruning, staking and guying procedures |
Inspects and records landscaping establishment |
Applies native plant laws and xeriscape principles |
| Describes pruning, staking and guying procedures |
Defines and applies highway planting methods |
Conducts nursery plant inspection |
| Explains landscaping establishment |
| Seeding |
Explains soil preparation, tillage, mulch, tackifiers and crimping |
Calculates application rates |
Reviews inspection records and recommends acceptance or rejection of application rates, seeds, soil preparation, tillage, mulch, tackifiers and crimping methods |
Accepts or rejects application rates, seeds, soil preparation, tillage, mulch, tackifiers and crimping methods |
| Describes hydro-seeding, broadcast and drilling methods |
Recognizes types of seeds |
| Describes the 3 classes of seeding |
Differentiates characteristics of pure live seed |
| Inspects and documents seeds/pure live seeds |
| Summarizes batch mixing |
| Inspects and documents soil preparation, tillage, mulch, tackifiers and crimping methods |
| Irrigation Systems |
Identifies controllers, pipe, filters, flow monitor, pressure regulator, emitters, sprinklers, valves, backflow preventer |
Inspects controllers, pipe, filters, flow monitor, pressure regulator, emitters, sprinklers, valves and backflow preventers |
Recommends acceptance or rejection of water sources, layout, backflow prevention and equipment including controllers, filters emitters, sprinklers, flow monitors, pressure regulators, and valves (master, remote control, pressure release, isolation, check and blow off valve) testing |
Accepts or rejects water sources, layout, backflow prevention and equipment including controllers, filters emitters, sprinklers, flow monitors, pressure regulators, and valves |
| Describes the function of each component |
Documents the function, condition, type of pipe and correct pipe joint methods |
| Identifies the water source |
Inspects and documents the water source |
| Observes and documents irrigation testing |
| Landscape Incidentals |
Explains landscape plans and layouts |
Inspects and documents the application of herbicides and pesticides |
Reviews and accepts or rejects documentation of the application of herbicides and pesticides and landscape design principles |
Accepts or rejects the application of herbicides and pesticides, plating and graphics and landscape design principles |
| Identifies the application of herbicides and pesticides |
Confirms and records the layout of graphics and inert materials as well as grade preparation, sampling, color acceptance, landscape graphics and measurement |
| Explains grade preparation, sampling, landscape graphics, color acceptance and measurement |